 Cynwyd Station is the end of the Cynwyd Line on SEPTA |
:: Exterior Photos of the Cynwyd Station - from 1910 to the present ::
|
:: Interior Photos - before Revitalization ::
|
:: May 2008 - Stabilization of the basement ::
|
:: May 2008 - First Floor Removed ::
|
:: June 2008: Support walls, first floor joists ::
|
:: July 2008: Floors and Framing; New Sill Plates for the Waiting Room ::
|
:: August & September 2008 - Support Continues ::
|
:: September 2008 ::
|
:: October 2008 ::
|
:: November 2008 ::
|
:: January 2009 - Cynwyd Station Revitalization ::
|
:: May 2009 - New contractor is on the job ::
|
:: June 2009 - Cynwyd Station revitalization ::
|
:: July 2009 - Cynwyd Train Station ::
|
:: Cynwyd Station August 2009 ::
|
:: September 2009 - Starting a Dormer on the Cynwyd Station ::
|
:: Cynwyd Station - Closing the outside, Oct. 2009 ::
|
:: November 2009 - Cynwyd Station ::
|
:: December work on the roof of the Cynwyd Station ::
|
:: January 2010 construction at Cynwyd Station ::
|
:: March 2010 - Roof, Fire Suppression and water piping ::
|
:: Cynwyd Station April 2010 ::
|
:: May 2010 - Sprinklers in Place, Insulation ::
|
:: Cynwyd Station, June 2010 ::
|
:: Cynwyd Station nearing completion of phase I - July 2010 ::
|
:: August at the Cynwyd Station - Sewer Line, finishing touches ::
|
:: Temporary Certificate of Occupancy Granted! ::
|
:: October at the Cynwyd Station ::
|
:: Dirt pile is removed from the Cynwyd Station ::
|
:: PennDot and Septa work on the surroundings - May & June 2012 ::
|
:: More PennDot work by Marino Corp ::
|
:: Construction at the Cynwyd Station, June 25-29, 2012 ::
|
:: Cynwyd Station Construction July 1-3 ::
|
:: Night and day at the Cynwyd Station ::
|