>> May 16, 2008
tree view
| thumbnails |
slideshow
May 16, 2008
.
Tile surround for baths coming along. Floor is finished upstairs.
Bamboo for kitchen came in and is already installed!!! Kitchen cabinets were delayed but now can be installed.
Gutters were also slapped up... and stairs were finished, along with the rest of the window and door trim.
.
DSCN4869.JPG
DSCN4870.JPG
DSCN4871.JPG
DSCN4872.JPG
DSCN4873.JPG
DSCN4874.JPG
DSCN4875.JPG
DSCN4876.JPG
DSCN4877.JPG
DSCN4878.JPG
DSCN4879.JPG
DSCN4880.JPG
DSCN4881.JPG
DSCN4882.JPG
DSCN4883.JPG
DSCN4884.JPG
DSCN4885.JPG
DSCN4886.JPG
DSCN4887.JPG
DSCN4888.JPG
DSCN4889.JPG
DSCN4890.JPG
DSCN4891.JPG
comment
|
share
Type your message and click Add Comment
It is best to
login
or
register
first but you may post as a guest.
Enter an optional name and contact email address.
Name
Name
Email
help
private comment
Type your message and click Add Comment
It is best to
login
or
register
first but you may post as a guest.
Enter an optional name and contact email address.
Name
Name
Email
help
private comment
click on thumbnails for full image